Welcome to MCL Building and Civil Engineering Ltd.
I wish to take this opportunity to introduce ourselves to you. MCL Building and Civil Engineering Limited are based at Kirkpatrick Fleming, near Gretna. We were incorporated in April 2011 and as a company have experience in carrying out all aspects of building and civil engineering work.
Please have a look at the Contract Examples on the website such as Kemper Waterproofing, Wind Farm Control Buildings and Turbine Bases, Civil Engineering and Internal Finishing. We work for a number of national Contractors including R J McLeod, Jones Bros, I & H Brown and Raymond Brown and clients direct including EDF-ER and RES.
I personally have 33 years experience in the construction industry and am a fully qualified Joiner by trade. Our ranges of services are designed to suit your needs, from shuttering Joiners, Steelfixers, concreting, 1st and 2nd fix Joinery, Plastering, Roofing, Plant Operators, Ground Workers and Kemper Waterproofing.
Our attention to detail and our friendly, experienced and fully insured staff have managed to create a thriving business with an impeccable reputation.
Please contact us by telephone on 01461 800318 or by email at info@mcl-building.co.uk to discuss any future working relationship.
Latest News
Still here!!
Started work shuttering retaining walls for Story construction at a new Aldi store in Carlisle today.
Received tender docs from I&H Brown for a framework contract with a wind farm operator yesterday.
Happy New Year!!!
Sorry I forgot to blog yesterday.
To excited about being back at work!!!
Secured the job from Story Construction in Carlisle.
Off for a fortnight
That's it, all doors fitted at Dungavel.
Target reached.
Big thanks to all the lads who have worked so hard this year.
Thank you to all our clients who keep us busy all year.
See you all in the 2015.
Pricing
Received tender docs from Land Engineering ltd for a job in East Kilbride.
Tis was the night before!!!
Doors getting fitted at Dungavel.
Elevation scaffolds dismantled.
Decoration partially complete.
On target for wind and water tight and secure for Xmas break.
Featured Projects
HESPIN WOOD RECYCLE CENTRE
SITE NAME - HESPIN WOOD RECYCLING CENTRE
JOB DESCRIPTION - FIRST AND SECOND FIX JOINERY AND DECORATION
LOCATION - CARLISLE
CLIENT - SHANKS
PRINCIPAL CONTRACTOR - HANSON CONTRACTING
DURATION - 4 WEEKS
COVERAGE - 2000M2
...
KELBURN WIND FARM
SITE NAME - KELBURN WIND FARM
JOB DESCRIPTION - DIG OUT ROUND PEDESTAL AND KEMPER WATERPROOFING TO 14NO. TURBINES
LOCATION - FAIRLIE
CLIENT - RES
PRINCIPAL CONTRACTOR - RES
DURATION - 2 WEEKS
COVERAGE - 400M2
...
BIO OIL FUEL PLANT - CIVILS
SITE NAME - BUSLINGTHORPE GREEN
JOB DESCRIPTION - DUCT INSTALL, RE BAR FIX, SHUTTERING, CONCRETING AND BLOCK LAYING
LOCATION - LEEDS
CLIENT -
PRINCIPAL CONTRACTOR - FREEDOM/AGRILEK
DURATION - 8 WEEKS
CONCRETE LAID - 40M2
...
MILLOUR WIND FARM
SITE NAME - MILLOUR WIND FARM
JOB DESCRIPTION - CONSTRUCTION OF TRADITIONAL CONTROL BUILDING
LOCATION - DALRY
CLIENT - COMMUNITY WIND
PRINCIPAL CONTRACTOR - JONES BROS
DURATION - 12 WEEKS
FLOOR AREA - 88M2
...
SOWERBY WOOD RECYCLE CENTRE
SITE NAME - SOWERBY WOOD RECYCLING CENTRE
JOB DESCRIPTION - RE BAR FIX AND SHUTTERING TO BASES, WALLS, SOFFITS, GROUND BEAMS AND PILE CAPS
LOCATION - BARROW
CLIENT - SHANKS
PRINCIPAL CONTRACTOR - HANSON CONTRACTING
DURATION - 26 WEEKS
FORMWORK / TONNAGE - 3500M2 / 220T
...