Contract Examples

View All >> CIVIL ENGINEERING

  FALLAGO RIG WIND FARM
.
SITE NAME - FALLAGO RIG WIND FARM JOB DESCRIPTION - SUPERVISION OF CONSTRUCTION OF TRANSFORMER PLINTHS AND ASSOCIATED WORKS LOCATION - DUNS CLIENT - EDF-ER PRINCIPAL CONTRACTOR - RJ MCLEOD DURATION - 8 WEEKS ... read more
  GREENRIGG WIND FARM
.
SITE NAME - GREENRIGG WIND FARM JOB DESCRIPTION - MAKE, ERECT AND STRIP FORMWORK FOR TURBINE PEDESTALS TO 16NO. TURBINES LOCATION - HEXHAM CLIENT - EDF-ER PRINCIPAL CONTRACTOR - BARR DURATION - 4 WEEKS FORMWORK - 488M2M2 ... read more
  ALDI STORE, CARLISLE
No Image
SITE NAME - ALDI STORE, DALSTON ROAD, CARLISLE JOB DESCRIPTION - SHUTTERING RETAINGING WALLS LOCATION - CARLISLE CLIENT - ALDI STORES PRINCIPAL CONTRACTOR - STORY CONSTRUCTION DURATION - 3 WEEKS FORMWORK - 400M2 ... read more
  WEST BROWNCASTL WIND FARM
No Image
SITE NAME - WEST BROWNCASTLE WIND FARM JOB DESCRIPTION - RE BAR FIX, SHUTTER AND CONCRETE 2NO. HEADWALLS LOCATION - STRATHAVEN CLIENT - PRINCIPAL CONTRACTOR - RJ MCLEOD DURATION - 2 WEEKS FORMWORK - 70M2 ... read more
  COLD NORTHCOTT WIND FARM
No Image
SITE NAME - COLD NORTHCOTT WIND FARM JOB DESCRIPTION - TURBINE GROUT REMEDIALS AND WATERPROOFING LOCATION - CORNWALL CLIENT - EDF-ER PRINCIPAL CONTRACTOR - MCL BUILDING AND CIVIL ENGINEERING LTD DURATION - 1 WEEK ... read more
  LLANWYRFON WIND FARM
No Image
SITE NAME - LLANWYRFON WIND FARM JOB DESCRIPTION - DIG OUT, RE BAR FIX, SHUTTER, CONCRETE AND BACKFILL STAIR BASES AT 13NO. TURBINES LOCATION - ABERYSTWYTH CLIENT - EDF-ER PRINCIPAL CONTRACTOR - MCL BUILDING AND CIVIL ENGINEERING LTD DURATION - 1 WEEK ... read more
  PARK SPRINGS WIND FARM
No Image
SITE NAME - PARK SPRINGS WIND FARM JOB DESCRIPTION - GROUTING BOLT RING AND CONCRETE PEDESTAL TO 3NO. TURBINES LOCATION - BARNSLEY CLIENT - EDF-ER PRINCIPAL CONTRACTOR - C A BLACKWELL DURATION - 2 WEEKS GROUT POURED - 4M3... read more
  GLENMUCKLOCH QUARRY
No Image
SITE NAME - GLENMUCKLOCH QUARRY JOB DESCRIPTION - RE BAR FIX, SHUTTER AND KEMPER WATERPROOF TWO TURBINE BASES LOCATION - SANQUHAR CLIENT - HARGREAVES PRINCIPAL CONTRACTOR - W E LAMMIE DURATION - 4 WEEKS TONNAGE - 10T ... read more
  PEARIE LAW WIND FARM
No Image
SITE NAME - PEARIE LAW WIND FARM JOB DESCRIPTION - GROUTING TO 6NO. GE TURBINE BOLT RINGS LOCATION - LIVINGSTON CLIENT - EDF-ER PRINCIPAL CONTRACTOR - I&H BROWN DURATION - 2 WEEKS GROUT POURED - 4M3 ... read more
  EWE HILL 6 WIND FARM
No Image
SITE NAME - EWE HILL 6 WIND FARM JOB DESCRIPTION - DUCT INSTALL, CASTING 6NO. REINFORCED CONCRETE TRANSFORMER BASES AND 6NO. STAIR BASES LOCATION - NR LOCKERBIE CLIENT - SCOTTISH POWER RENEWABLES PRINCIPAL CONTRACTOR - I&H BROWN DURATION - 4 WEEKS CONCRETE POURED - 72M3 ... read more

  page 1 2 Next -> Last ->>

.