  SCOTTS CONCRETE SLABS
No Image
SITE NAME - SCOTTS PEAT WORKS JOB DESCRIPTION - LAY REINFORCED CONCRETE SLABS AND DRAINAGE REPAIRS LOCATION - SPRINGFIELD CLIENT - SCOTTS PEAT PRINCIPAL CONTRACTOR - MCL BUILDING AND CIVIL ENGINEERING LTD DURATION - 4 WEEKS CONCRETE POURED - 200M3 STRUCTURAL FIBRE ... read more
  BARMOOR WIND FARM
No Image
SITE NAME - BARMOOR WIND FARM JOB DESCRIPTION - CONSTRUCTION OF 6NO. BRICK BUILT WITH INSULATED ROOF PANEL ETS BUILDINGS LOCATION - BERWICK CLIENT - EDF-ER PRINCIPAL CONTRACTOR - I&H BROWN DURATION - 6 WEEKS FLOOR AREAS - 91M2... read more
  MIDDLE BALBEGGIE WIND FARM
No Image
SITE NAME - MIDDLE BALBEGGIE WIND FARM JOB DESCRIPTION - CONSTRUCTION OF TRADITIONAL CONTROL BUILDING LOCATION - THORNTON CLIENT - AIRVOLUTION PRINCIPAL CONTRACTOR - RJ MCLEOD DURATION - 6 WEEKS FLOOR AREA - 59M2 ... read more
  BIO OIL FUEL PLANT - CIVILS
.
SITE NAME - BUSLINGTHORPE GREEN JOB DESCRIPTION - DUCT INSTALL, RE BAR FIX, SHUTTERING, CONCRETING AND BLOCK LAYING LOCATION - LEEDS CLIENT - PRINCIPAL CONTRACTOR - FREEDOM/AGRILEK DURATION - 8 WEEKS CONCRETE LAID - 40M2 ... read more
  HIGH HARRINGTON HOUSING SCHEME
No Image
SITE NAME - HIGH HARRINGTON HOUSING SCHEME JOB DESCRIPTION - RE BAR FIX AND FORMWORK FOR DEEP MANHOLES, ACCESS STAIRS, TRANSFORMER PLINTHS AND FITMENTS LOCATION - HIGH HARRINGTON, CUMBRIA CLIENT - ARMSTRONG HOMES PRINCIPAL CONTRACTOR - GBS DURATION - 26 WEEKS FORMWORK / TONNAGE - 400M2 / 6T   ... read more
  GORDONSTOWN WIND FARM
.
SITE NAME - GORDONSTOWN WIND FARM JOB DESCRIPTION - RE BAR FIX AND PERMANENT FORMWORK TO 4NO. TURBINE BASES LOCATION - KIRKTON OF AUCHTERLEES CLIENT - INFINNIS PRINCIPAL CONTRACTOR - JONES BROS DURATION - 6 WEEKS TONNAGE - 414T ... read more
  CALDER WATER WIND FARM
No Image
SITE NAME - CALDER WATER WIND FARM JOB DESCRIPTION - CONSTRUCTION OF TRADITIONAL CONTROL BUILDING LOCATION - STRATHAVEN CLIENT - COMMUNITY WIND PRINCIPAL CONTRACTOR - RJ MCLEOD DURATION - 6 WEEKS FLOOR AREA - 100M2... read more
  MOSSMORRAN WIND FARM
No Image
SITE NAME - MOSSMORRAN WIND FARM JOB DESCRIPTION - CONSTRUCTION OF TRADITIONAL CONTROL BUILDING LOCATION - COWDENBEATH CLIENT - AIRVOLUTION PRINCIPAL CONTRACTOR - RJ MCLEOD DURATION - 6 WEEKS FLOOR AREA - 59M2... read more
  PROJECT SEAL
No Image
  MILLOUR WIND FARM
.
SITE NAME - MILLOUR WIND FARM JOB DESCRIPTION - CONSTRUCTION OF TRADITIONAL CONTROL BUILDING LOCATION - DALRY CLIENT - COMMUNITY WIND PRINCIPAL CONTRACTOR - JONES BROS DURATION - 12 WEEKS FLOOR AREA - 88M2 ... read more

.